Earls Gate Energy Centre: Difference between revisions

From WikiWaste
(ownership and timing update)
No edit summary
Line 8: Line 8:
In March 2022 [[EQT]], the owner of Covanta, bought the interests of the [[Green Investment Group]] in this and three other projects ([[Rookery Pit Energy Recovery Facility (Rookery South)]], [[Protos EFW]], and [[Newhurst EFW]]) to leave [[Green Investment Group]] with no further interest in the projects<ref>https://www.endswasteandbioenergy.com/article/1748321/covanta-buys-gig-stakes-four-efw-plants</ref>.
In March 2022 [[EQT]], the owner of Covanta, bought the interests of the [[Green Investment Group]] in this and three other projects ([[Rookery Pit Energy Recovery Facility (Rookery South)]], [[Protos EFW]], and [[Newhurst EFW]]) to leave [[Green Investment Group]] with no further interest in the projects<ref>https://www.endswasteandbioenergy.com/article/1748321/covanta-buys-gig-stakes-four-efw-plants</ref>.


The facility has been developed by [[Brockwell Energy]], and will be operated by [[MES Environmental]] for a contract duration of 25 years. [[MES Environmental]] is now a subsidiary of [[Paprec]], having agreed to buy out [[CNIM]] in March 2021<ref>[https://cnim.com/sites/default/files/media/Communiqu%C3%A9s%20financiers/2021-03-25-CNIM-Communiqu%C3%A9-EN.pdf CNIM Press Release]</ref>.  
The facility was developed by [[Brockwell Energy]], and was originally planned to be operated by [[MES Environmental]] for a contract duration of 25 years. Subsequently [[Hitachi Zosen Inova]] were contracted to complete the construction of the plant and were awarded a 25 year contract to operate it<ref>https://www.hz-inova.com/hzi-wins-25-year-operations-maintenance-contract-at-the-earls-gate-waste-to-energy-centre/</ref>.


The [[EfW]] will replace an existing gas-fired energy plant on the site.
The [[EfW]] will replace an existing gas-fired energy plant on the site.


The facility was expected to become operational by the end of 2021<ref name="ref1" >Earls Gate Energy Centre, 2020. [https://earlsgateconstruction.co.uk/ Home - EARLS GATE ENERGY CENTRE. Online. [Accessed 21 Feb. 2020].]</ref> but has run into delays through the construction subsidiary of [[CNIM]] responsible for delivery of [[EfW]] projects running into financial difficulties in January 2022. This is also impacting a second plant under construction at [[Lostock Sustainable Energy Plant]]<ref>https://www.mrw.co.uk/news/mp-calls-to-halt-efw-as-builder-cnim-hits-financial-problems-28-01-2022/</ref>.
The facility was expected to become operational by the end of 2021<ref name="ref1" >Earls Gate Energy Centre, 2020. [https://earlsgateconstruction.co.uk/ Home - EARLS GATE ENERGY CENTRE. Online. [Accessed 21 Feb. 2020].]</ref> but ran into delays through the construction subsidiary of [[CNIM]] responsible for delivery of [[EfW]] projects running into financial difficulties in January 2022. This is also impacted a second plant under construction at [[Lostock Sustainable Energy Plant]]<ref>https://www.mrw.co.uk/news/mp-calls-to-halt-efw-as-builder-cnim-hits-financial-problems-28-01-2022/</ref>.
 
The plant was reported as becoming operational in May 2025 on the [[Hitachi Zosen Inova]] LinkedIn page<ref>https://www.linkedin.com/company/hitachi-zosen-inova-former-ae&e-inova-former-von-roll-inova-/posts/?feedView=all</ref>.


==Technology==
==Technology==
The moving-[[grate]] [[combustion]] technology will be provided by [[CNIM]]<ref name="ref2" >Brockwell Energy, 2020. [http://www.brockwellenergy.com/our-projects/energy-from-waste/earls-gate-energy-centre/ Brockwell Energy | Earls Gate Energy Centre. Online. Brockwellenergy.com. [Accessed 21 Feb. 2020].]</ref>.
The moving-[[grate]] [[combustion]] technology was provided by [[CNIM]]<ref name="ref2" >Brockwell Energy, 2020. [http://www.brockwellenergy.com/our-projects/energy-from-waste/earls-gate-energy-centre/ Brockwell Energy | Earls Gate Energy Centre. Online. Brockwellenergy.com. [Accessed 21 Feb. 2020].]</ref>.


==Construction==
==Construction==
[[CNIM]] is the [[EPC]] contractor for this facility, with [[Clugston]] in charge of the civil engineering. Construction commenced in January 2019 and is scheduled to take 3 years, with commissioning ending and operations beginning in 2021<ref name="ref1" />.  
[[CNIM]] was the original [[EPC]] contractor for this facility, with [[Clugston]] in charge of the civil engineering. Construction commenced in January 2019 and was scheduled to take 3 years, with commissioning ending and operations beginning in 2021<ref name="ref1" />. However, with [[CNIM]] falling into financial difficulty, and ultimate collapse, [[Hitachi Zosen Inova]] took over the completion of the construction and the [[O&M]] contract.


==Waste Input==
==Waste Input==

Revision as of 00:57, 22 May 2024

An EfW facility based upon conventional combustion technology, located at Earls Gate Park, Grangemouth in Scotland. The facility is forecast to have a maximum capacity of 215,000 tonnes per annum, and will be a Combined Heat and Power facility, exporting 21.5 MW electricity and heat to the nearby chemical company CalaChem and to other adjacent industrial plants, with any excess power fed into the national grid.

Earls Gate Energy Centre
Under Construction
Site Location
Site Location

See Residual EfW → page for a larger UK Wide map.

Waste Licence PPC/A/1157446
Operator Earls Gate Energy Centre Ltd
Region Scotland
Operational Capacity 274ktpa
Is site R1? No
When was R1 Granted?
What was the R1 value 0.00
Electrical Capacity 21.60MWe
Number of Lines 0
Number of Turbines 0
CHP Yes
Technology Approach EfW Incineration
Funding Type Merchant

Operators Annual Report


Input Data

Year HH C&I Clin RDF Total


Output Data

Year IBA IBA %ge of Tot IN APC APC %ge of Tot IN

Earls Gate Energy Centre. Biothek Ecologic Fuel, 2018.
Earls Gate Energy Centre. Biothek Ecologic Fuel, 2018.

[1]


Summary

An EfW facility based upon conventional combustion technology, located at Earls Gate Park, Grangemouth in Scotland. The facility is forecast to have a maximum capacity of 215,000 tonnes per annum, and will be a Combined Heat and Power facility, exporting 21.5 MW electricity and heat to the nearby chemical company CalaChem and to other adjacent industrial plants, with any excess power fed into the national grid. The cost of the project is circa £200m, which was provided by the investors Brockwell Energy, the Green Investment Group and Covanta.

In March 2022 EQT, the owner of Covanta, bought the interests of the Green Investment Group in this and three other projects (Rookery Pit Energy Recovery Facility (Rookery South), Protos EFW, and Newhurst EFW) to leave Green Investment Group with no further interest in the projects[2].

The facility was developed by Brockwell Energy, and was originally planned to be operated by MES Environmental for a contract duration of 25 years. Subsequently Hitachi Zosen Inova were contracted to complete the construction of the plant and were awarded a 25 year contract to operate it[3].

The EfW will replace an existing gas-fired energy plant on the site.

The facility was expected to become operational by the end of 2021[4] but ran into delays through the construction subsidiary of CNIM responsible for delivery of EfW projects running into financial difficulties in January 2022. This is also impacted a second plant under construction at Lostock Sustainable Energy Plant[5].

The plant was reported as becoming operational in May 2025 on the Hitachi Zosen Inova LinkedIn page[6].

Technology

The moving-grate combustion technology was provided by CNIM[7].

Construction

CNIM was the original EPC contractor for this facility, with Clugston in charge of the civil engineering. Construction commenced in January 2019 and was scheduled to take 3 years, with commissioning ending and operations beginning in 2021[4]. However, with CNIM falling into financial difficulty, and ultimate collapse, Hitachi Zosen Inova took over the completion of the construction and the O&M contract.

Waste Input

The facility will accept residual waste as feedstock.

References