An [[EfW]] facility based upon conventional combustion technology and considered an [[ERF]] based on its [[R1]] status. Greatmoor has permitted operational capacity of 345,000 tonnes per annum, operated by [[FCC Environment]] in a partnership with [[Buckinghamshire  County Council]] . Delivery of waste is by road and the facility processes primarily residual [[Household Waste]] and some [[Commercial Waste]]<ref>[https://www.greatmoor.co.uk/greatmoor-energy-from-waste/ Greatmoor Energy from Waste Website]</ref>.
 
{{EfWTemplate|EPR={{#var:epr}}|id=13}}
[[File:FCC Greatmoor.png|270px|left|FCC Greatmoor]] __TOC__
<br clear='left' />
==Summary==
==Summary==
An [[EfW]] facility based upon conventional combustion technology and considered an [[ERF]] based on its [[R1]] status. Greatmoor has permitted operational capacity of 345,000 tonnes per annum, operated by [[FCC Environment]] in a partnership with [[Buckinghamshire  County Council]] . Delivery of waste is by road and the facility processes primarily residual [[Household Waste]] and some [[Commercial Waste]]<ref>[https://www.greatmoor.co.uk/greatmoor-energy-from-waste/ Greatmoor Energy from Waste Website]</ref>.  
An [[EfW]] facility based upon conventional combustion technology and considered an [[ERF]] based on its [[R1]] status. Greatmoor has permitted operational capacity of 345,000 tonnes per annum, operated by [[FCC Environment]] in a partnership with [[Buckinghamshire  County Council]] . Delivery of waste is by road and the facility processes primarily residual [[Household Waste]] and some [[Commercial Waste]]<ref>[https://www.greatmoor.co.uk/greatmoor-energy-from-waste/ Greatmoor Energy from Waste Website]</ref>.  
Line 8: Line 10:
==History==
==History==
The Greatmoor facility was built primarily to service a 30 year [[PFI]] contract signed in April 2013 with [[Buckinghamshire  County Council]], with anticipated total throughput of up to 345,000 tonnes per annum. It is located on [[FCC Environment]]'s [[Calvert]] [[Landfill]] in the north of Buckinghamshire<ref>[http://www.fccenvironment.co.uk/green-energy/greatmoor-efw/ FCC Environment Website]</ref>.
The Greatmoor facility was built primarily to service a 30 year [[PFI]] contract signed in April 2013 with [[Buckinghamshire  County Council]], with anticipated total throughput of up to 345,000 tonnes per annum. It is located on [[FCC Environment]]'s [[Calvert]] [[Landfill]] in the north of Buckinghamshire<ref>[http://www.fccenvironment.co.uk/green-energy/greatmoor-efw/ FCC Environment Website]</ref>.
In 2020 [[FCC]] formed [[Green Recovery Projects Ltd]], a new company for its [[Energy from Waste]] portfolio to allow the subsequent sale of 49% to [[Icon Infrastructure]]. This included Greatmoor EfW<ref>[https://www.letsrecycle.com/news/latest-news/icon-infrastructure-share-fcc-energy-from-wastes-energy-from-waste-plants/ Letsrecycle Article]</ref>.


==Plant==
==Plant==
Built by [[Hitachi Zosen Inova]] under a Design & Build [[EPC]]-turnkey contract . Construction started in September 2013 and was completed in June 2016 at a reported<ref>[http://www.hz-inova.com/cms/wp-content/uploads/2016/05/Buckinghamshire_Online_E.pdf Hitachi Zosen Inova Website]</ref> GBP £210m capital cost.
Built by [[Hitachi Zosen Inova]] under a Design & Build [[EPC]]-turnkey contract . Construction started in September 2013 and was completed in June 2016 at a reported<ref>[https://www.hz-inova.com/projects/buckinghamshire-uk/ Hitachi Zosen Inova Website]</ref> GBP £210m capital cost.
The plant comprises 1 line of 37.5 tonnes/hour (maximum 39.4 tonnes/hour) with a design capacity capable of treating 300,000 tonnes per annum via standard combustion technology, air cooled, Hitachi Zosen Inova Grate, generating super-heated steam, and is configured to run on residual [[Household Waste]] and [[Commercial Waste]] with a [[CV]] of between 7.5 and 12.5MJ/kg delivering between 27.7 MWe and 29.4 MWe output with up to 6.6 MWth of district heating output.
The plant comprises 1 line of 37.5 tonnes/hour (maximum 39.4 tonnes/hour) with a design capacity capable of treating 300,000 tonnes per annum via standard combustion technology, air cooled, Hitachi Zosen Inova Grate, generating super-heated steam, and is configured to run on residual [[Household Waste]] and [[Commercial Waste]] with a [[CV]] of between 7.5 and 12.5MJ/kg delivering between 27.7 MWe and 29.4 MWe output with up to 6.6 MWth of district heating output.


==Local Authority Users==
{{EfWLAData|EPR={{#var: epr}}}}
The following  represents those local authorities recorded as putting tonnage into the site (either directly or via a transfer station). The tonnage received cannot be directly compared with the stated historical tonnage received and recorded in the [[EA]] statistics as these are recorded on a calendar year basis (i.e. January 2018 to December 2018). A 'zero return' below indicates no local authority tonnage was recorded, most likely a result of the plant being recently commissioned and actually having received no tonnage. Equally, lower than expected tonnage maybe a result of either a new plant being in 'ramp up' towards full capacity after construction, or may be a result of plant shut down and subsequent re-start in a year.
{{EAIn|EPR={{#var: epr}}}}
{{#clear_external_data:}}
{{#get_db_data: db=engy
|from=wdfincin|where=epr='UP3734HT'|data=authority=authority,epr=epr,ton=ton}}
{|class="wikitable sortable"
! Authority