An [[EfW]] facility based upon conventional combustion technology and considered an [[ERF]] based on its [[R1]] status. Ardley has permitted operational capacity of 326,000 tonnes per annum, operated and owned by [[Viridor]]. Delivery of waste is by road and the facility processes primarily residual [[Household Waste]] and some [[Commercial Waste]]<ref>[https://www.viridor.co.uk/energy/energy-recovery-facilities/ardley-erf/ Viridor Website]</ref>
 
{{EfWTemplate|EPR={{#var:epr}}|id=15}}
[[File:Viridor Ardley.jpg|350px|left]]__TOC__
<br clear='left'/>
==Summary==
==Summary==
An [[EfW]] facility based upon conventional combustion technology and considered an [[ERF]] based on its [[R1]] status. Ardley has permitted operational capacity of 326,000 tonnes per annum, operated and owned by [[Viridor]]. Delivery of waste is by road and the facility processes primarily residual [[Household Waste]] and some [[Commercial Waste]]<ref>[https://www.viridor.co.uk/energy/energy-recovery-facilities/ardley-erf/ Viridor Website]</ref>
An [[EfW]] facility based upon conventional combustion technology and considered an [[ERF]] based on its [[R1]] status. Ardley has permitted operational capacity of 326,000 tonnes per annum, operated and owned by [[Viridor]]. Delivery of waste is by road and the facility processes primarily residual [[Household Waste]] and some [[Commercial Waste]]<ref>[https://www.viridor.co.uk/energy/energy-recovery-facilities/ardley-erf/ Viridor Website]</ref>
Line 11: Line 13:
==Plant==
==Plant==
Built by a JV between [[CNIM]] and [[Clugson]] under a Design & Build [[EPC]]-turnkey contract which started in March 2011 and was delivered in November 2014<ref>[https://cnim.com/en/turnkey-energy-recovery-facility-oxford CNIM Website]</ref> at a reported <ref>[http://haggaiprojects.co.uk/efw-projects/4594784023 Haggai Projects Website]</ref> £220m capital cost.
Built by a JV between [[CNIM]] and [[Clugson]] under a Design & Build [[EPC]]-turnkey contract which started in March 2011 and was delivered in November 2014<ref>[https://cnim.com/en/turnkey-energy-recovery-facility-oxford CNIM Website]</ref> at a reported <ref>[http://haggaiprojects.co.uk/efw-projects/4594784023 Haggai Projects Website]</ref> £220m capital cost.
The plant comprises 2 lines of 20 tonnes/hour design capacity capable of treating 300,000 tonnes per annum via standard combustion technology Martin reverse acting grate, generating super-heated steam, and is configured to run on primarily residual [[Household Waste]]
The plant comprises 2 lines of 20 tonnes/hour design capacity capable of treating 300,000 tonnes per annum via standard combustion technology Martin Reverse Acting Grate, generating super-heated steam, and is configured to run on primarily residual [[Household Waste]]
 
==Local Authority Users==


{{EfWLAData|EPR={{#var: epr}}}}
{{EAIn|EPR={{#var: epr}}}}