Margam Green Energy Plant: Difference between revisions
m →Plant |
|||
Line 11: | Line 11: | ||
The plant became operational in 2019 at a cost of c.£160m<ref name="Marg" />. | The plant became operational in 2019 at a cost of c.£160m<ref name="Marg" />. | ||
The Margam plant takes waste wood that is supplied by Stobart Biomass on a long term contract. The waste wood is sourced and supplied by Stobart from across the country at a rate of approximately 6,000 tonnes per week | The Margam plant takes waste wood that is supplied by Stobart Biomass on a long term contract. The waste wood is sourced and supplied by Stobart from across the country at a rate of approximately 6,000 tonnes per week<ref name="Marg" /> with the plant having an annula combustion rate of c.335,000tonnes of wood waste per annum<ref name="BVV">[http://www.volund.dk/Biomass_energy/References/Margam/ B&W Volund]</ref>. | ||
==Plant== | ==Plant== |