Cauldon Cement Kiln: Difference between revisions
m add new link |
|||
Line 24: | Line 24: | ||
The Cauldon site waste return to the [[EA]] for the most recent year showed the following wastes used on site, which were used primary for the purpose of substituting fuel requirements in the plant: | The Cauldon site waste return to the [[EA]] for the most recent year showed the following wastes used on site, which were used primary for the purpose of substituting fuel requirements in the plant: | ||
{{CKWaste|EPR=TP3334AW}} | {{CKWaste|EPR=TP3334AW}} | ||
In early June 2021 [[Aggregate Industries]] confirmed that they had broken ground on a £13m project to increase their ability to handle up to 100,000 tonnes per annum of [[RDF|waste derived fuel]] from early 2020<ref>[https://www.aggregate.com/news-and-resources/press-releases/cauldon-cement-plant-breaks-ground Aggregate Industries Press Release Accessed 11th June 2021]</ref> | |||
==References== | ==References== | ||
<references /> | <references /> |