[[Clinical Waste Incinerator]] operated by [[Tradebe]] Healthcare National Ltd and located in Wrexham, Clwyd, North Wales. It is a Waste-to-Energy facility with an annual permitted capacity of c. 8,000 tonnes<ref name="web">https://www.tradebe.co.uk/clinical-waste-incineration</>. | [[Clinical Waste Incinerator]] operated by [[Tradebe]] Healthcare National Ltd and located in Wrexham, Clwyd, North Wales. It is a Waste-to-Energy facility with an annual permitted capacity of c. 8,000 tonnes<ref name="web">https://www.tradebe.co.uk/clinical-waste-incineration</ref>. | ||
==Plant<ref name="Adden">Annual Performance Report 2020</ref>== | ==Plant<ref name="Adden">Annual Performance Report 2020</ref>== | ||
Line 13: | Line 13: | ||
{{EAIn|EPR={{#var:epr}}}} | {{EAIn|EPR={{#var:epr}}}} | ||
==References== | ==References== |
Revision as of 11:58, 18 June 2021
Clinical Waste Incinerator operated by Tradebe Healthcare National Ltd and located in Wrexham, with an annual capacity of c. 8,000 tonnes.
Wrexham Clinical Waste Incinerator | |
See HT & Clin → page for a larger UK Wide map. | |
Waste Licence | WP3836ZF |
Operator | Tradebe |
Operational Capacity | 8,000tpa |
Number of Lines | 1 |
Region | Wales |
Annual Report Data
Year | Total In | Total Clinical | IBA Out | ACP Out | Op Hours
|
---|---|---|---|---|---|
2019 | 5605 | 5605 | 458 | 86 | |
2018 | |||||
2017 | |||||
2020 | 0 | 0 | 0 | 0 | 0 |
2021 | 5124 | 5124 | 761 | 317 | 0 |
2022 | 4738 | 4738 | 840 | 351 | 0 |
Summary
Clinical Waste Incinerator operated by Tradebe Healthcare National Ltd and located in Wrexham, Clwyd, North Wales. It is a Waste-to-Energy facility with an annual permitted capacity of c. 8,000 tonnes[1].
Plant[2]
Text to follow
Error: Could not connect to database (Cannot access the database: Unable to connect to PostgreSQL server: connection to server at "10.106.0.2", port 5432 failed: SSL SYSCALL error: EOF detected).Error: Could not connect to database (Cannot access the database: Unable to connect to PostgreSQL server: connection to server at "10.106.0.2", port 5432 failed: FATAL: the database system is in recovery mode).Error: Could not connect to database (Cannot access the database: Unable to connect to PostgreSQL server: connection to server at "10.106.0.2", port 5432 failed: FATAL: the database system is in recovery mode).
Waste Tonnage, By Origin
The table shows a list of the Waste for the Permit WP3836ZF, that has arrived into sites as reported to the Regulator and then publicised in their reported statistics. The Data used is from the most recent returns. The total reported tonnage arriving at the site was: Expression error: Unexpected < operator.t.
Where this tonnage exceeds that reported in year of the corresponding annual report, this may be due to the following reasons:
- Tonnage may have been received but not incinerated, i.e. the material is held pending incineration (the operator return to the EA reports as received whereas the annual report focuses on when the waste is incinerated.)
- Material may have been received into the site but treated in some other way than incineration.
- Material may have been received on the but transferred out of site for disposal/treatment at another site rather than incineration on the site.
EWC Code | Origin of Waste | Tonnes In |
---|
References
- ↑ https://www.tradebe.co.uk/clinical-waste-incineration
- ↑ Annual Performance Report 2020