The key elements of MRF design and operation include:
The key elements of MRF design and operation include:
* Throughput capacity - measured in both weight and volume due to differing bulk densities of materials that impact the sorting machinery specification and the capacity of conveyors and storage areas  
* Throughput capacity - measured in both weight and volume due to differing bulk densities of materials that impact on the design of the sorting machinery, capacity of conveyors and storage areas  
* Reliability - the operational availability of the plant and the time required to maintain it
* Reliability - the operational availability of the plant and the time required to maintain it
* Quality of Outputs - high quality outputs ensure a solid, higher value market for the materials recovered
* Quality of Outputs - high quality outputs ensure a solid, higher value market for the materials recovered
Line 43: Line 43:
|}
|}


The [[MRF Code of Practice]] applies to all 'Qualifying MRFs' which are those all those MRFs that receive more than 1,000 tonnes per annum of primarily [[DMR]] materials from households and other sources with a similar composition. This has allowed the performance of MRFs t be compared, including the level of contamination and associated rejects from each MRF.  
The [[MRF Code of Practice]] applies to all 'Qualifying MRFs' which are those all those MRFs that receive more than 1,000 tonnes per annum of primarily [[DMR]] materials from households and other sources with a similar composition. This has allowed the performance of MRFs to be compared, including the level of contamination and associated rejects from each MRF.  


A list of these MRFs and associated map is set out below which are, on the whole, '''"Clean" MRFs'''.  
A list of these MRFs and associated map is set out below which are, on the whole, '''"Clean" MRFs'''.