Built by a JV between [[CNIM]] and [[Clugson]] under a Design & Build [[EPC]]-turnkey contract which started in March 2011 and was delivered in November 2014<ref>[https://cnim.com/en/turnkey-energy-recovery-facility-oxford CNIM Website]</ref> at a reported <ref>[http://haggaiprojects.co.uk/efw-projects/4594784023 Haggai Projects Website]</ref> £220m capital cost.
Built by a JV between [[CNIM]] and [[Clugson]] under a Design & Build [[EPC]]-turnkey contract which started in March 2011 and was delivered in November 2014<ref>[https://cnim.com/en/turnkey-energy-recovery-facility-oxford CNIM Website]</ref> at a reported <ref>[http://haggaiprojects.co.uk/efw-projects/4594784023 Haggai Projects Website]</ref> £220m capital cost.
The plant comprises 2 lines of 20 tonnes/hour design capacity capable of treating 300,000 tonnes per annum via standard combustion technology Martin reverse acting grate, generating super-heated steam, and is configured to run on primarily residual [[Household Waste]]
The plant comprises 2 lines of 20 tonnes/hour design capacity capable of treating 300,000 tonnes per annum via standard combustion technology Martin Reverse Acting Grate, generating super-heated steam, and is configured to run on primarily residual [[Household Waste]]