Tansterne: Difference between revisions

Northern Chick (talk | contribs)
No edit summary
Northern Chick (talk | contribs)
No edit summary
Line 2: Line 2:
{{Biomass Plant|NAME=Tansterne|id=79}}
{{Biomass Plant|NAME=Tansterne|id=79}}
==Summary==
==Summary==
A Biomass Waste EFW facility based on c.150,000 tonnes per annum of waste wood generating 22MW of electricity to the grid<ref>[https://solar21.ie/projects/biomass-21/ Solar 21 Biomass]</ref>
A Biomass Waste EFW facility based on c.150,000 tonnes per annum of waste wood generating 22MW of electricity to the grid and located in Tansterne near Hull.<ref name=>[https://solar21.ie/projects/biomass-21/ Solar 21 Biomass]</ref>
 
It is operated by [[Solar 21]] and became fully operational in Februaury 2018.
 
==Plant==
In September 2019 the O&M contractor HRS Energy Tansterne Ltd (HRSET) went into administration. HRSET had originally held the O&M contract until it expired on 01/09/73.the plant is now owner-operated by GIB-Bio Ltd which is a subsidiary of Solar 21, the owners of the facility.


==Refernces==
==Refernces==