A Biomass Waste EFW facility based on c.150,000 tonnes per annum of waste wood generating 22MW of electricity to the grid<ref>[https://solar21.ie/projects/biomass-21/ Solar 21 Biomass]</ref>
A Biomass Waste EFW facility based on c.150,000 tonnes per annum of waste wood generating 22MW of electricity to the grid and located in Tansterne near Hull.<ref name=>[https://solar21.ie/projects/biomass-21/ Solar 21 Biomass]</ref>
 
It is operated by [[Solar 21]] and became fully operational in Februaury 2018.
 
==Plant==
In September 2019 the O&M contractor HRS Energy Tansterne Ltd (HRSET) went into administration. HRSET had originally held the O&M contract until it expired on 01/09/73.the plant is now owner-operated by GIB-Bio Ltd which is a subsidiary of Solar 21, the owners of the facility.


==Refernces==
==Refernces==

Revision as of 04:58, 8 April 2020

Template:Biomass Plant

Summary

A Biomass Waste EFW facility based on c.150,000 tonnes per annum of waste wood generating 22MW of electricity to the grid and located in Tansterne near Hull.[1]

It is operated by Solar 21 and became fully operational in Februaury 2018.

Plant

In September 2019 the O&M contractor HRS Energy Tansterne Ltd (HRSET) went into administration. HRSET had originally held the O&M contract until it expired on 01/09/73.the plant is now owner-operated by GIB-Bio Ltd which is a subsidiary of Solar 21, the owners of the facility.

Refernces