Environmental Permitting (England and Wales) (Amendment) Regulations 2023: Difference between revisions

From Wikiwaste
Northern Chick (talk | contribs)
Replaced content with "Category: Legislation & Policy From October 2024 these new regulations will bring more waste facilities under the scope of the Material Facility (MF) regulations than previously. The amended regulations bring into scope facilities which receive single waste streams and facilities which consolidate waste material into bulk quantities. the regulations place the onus on the operator of the site to self-assess whether their facility is a MF under the reg..."
Tag: Replaced
Northern Chick (talk | contribs)
More succint overview of the legislation.
Line 1: Line 1:
[[Category: Legislation & Policy]]
[[Category: Legislation & Policy]]


From October 2024 these new regulations will bring more [[waste]] facilities under the scope of the [[Material Facility]] (MF) regulations than previously. The amended regulations bring into scope facilities which receive single [[waste]] streams and facilities which consolidate waste material into bulk quantities. the regulations place the onus on the operator of the site to self-assess whether their facility is a MF under the regulations<ref name=":0">https://www.gov.uk/guidance/materials-facilities-waste-sampling-and-reporting-from-october-2024</ref>.
These Regulations entered into force on 2nd October 2023 and amend the [[Environmental Permitting (England and Wales) Regulations 2016]] in respect to Sch 2 Part 9 relating to Waste Operations and Material Facilities.  


From October 2024 these amended [[MRF Regulations]] brought more [[waste]] facilities under the scope of the [[Material Facility]] (MF) regulations than previously. The amended regulations bring into scope facilities which receive single [[waste]] streams and facilities which consolidate waste material into bulk quantities. The regulations place the onus on the operator of the site to self-assess whether their facility is a MF under the regulations<ref name=":0">https://www.gov.uk/guidance/materials-facilities-waste-sampling-and-reporting-from-october-2024</ref>.
These new  [[MRF Regulations]] also increased the frequency of sampling from 125 tonnes previously to every 75 tonnes (per supplier). the sample weight does however remain at 60kg (minimum weight 55kg)<ref name=":0" />.
The number of input sampling categories also increased from four to ten and material facilities now need to record where the waste material is from.
Packaging and deposit return schemem (DRS) material proportions must also be sampled and reported.


==References==
==References==
<references />
<references />

Revision as of 15:02, 27 March 2025


These Regulations entered into force on 2nd October 2023 and amend the Environmental Permitting (England and Wales) Regulations 2016 in respect to Sch 2 Part 9 relating to Waste Operations and Material Facilities.

From October 2024 these amended MRF Regulations brought more waste facilities under the scope of the Material Facility (MF) regulations than previously. The amended regulations bring into scope facilities which receive single waste streams and facilities which consolidate waste material into bulk quantities. The regulations place the onus on the operator of the site to self-assess whether their facility is a MF under the regulations[1].

These new MRF Regulations also increased the frequency of sampling from 125 tonnes previously to every 75 tonnes (per supplier). the sample weight does however remain at 60kg (minimum weight 55kg)[1].

The number of input sampling categories also increased from four to ten and material facilities now need to record where the waste material is from.

Packaging and deposit return schemem (DRS) material proportions must also be sampled and reported.

References