Greatmoor EfW: Difference between revisions

From WikiWaste
(add page specific text)
m (expanded text)
Line 4: Line 4:


==Summary==
==Summary==
An [[EfW]] facility based upon conventional combustion technology and considered an [[ERF]] based on its [[R1]] status. Greatmoor has permitted operational capacity of 345,000 tonnes per annum, operated by [[FCC Environment]] in a partnership with [[Buckinghamshire  County Council]] . Delivery of waste is by road and the facility processes primarily residual [[Household Waste]] and some [[Commercial Waste]]<ref>[https://www.greatmoor.co.uk/greatmoor-energy-from-waste/ Greatmoor Energy from Waste Website]</ref>.


==History==
==History==
The Greatmoor facility was built primarily to service a 30 year [[PFI]] contract signed in April 2013 with [[Buckinghamshire  County Council]], with anticipated total throughput of up to 345,000 tonnes per annum. It is located on [[FCC Environment]]'s [[Calvert]] [[Landfill]] in the north of Buckinghamshire<ref>[http://www.fccenvironment.co.uk/green-energy/greatmoor-efw/ FCC Environment Website]</ref>.


==Plant==
==Plant==

Revision as of 03:14, 6 February 2020

FCC Greatmoor
FCC Greatmoor


Greatmoor EfW
Operational
Site Location
Site Location

See Residual EfW → page for a larger UK Wide map.

Waste Licence UP3734HT
Operator FCC Environment
Region South East
Operational Capacity 345ktpa
Is site R1? Yes
When was R1 Granted? 2011-01-01
What was the R1 value 0.76
Electrical Capacity 32.00MWe
Number of Lines 1
Number of Turbines 1
CHP No
Technology Approach EfW Incineration
Funding Type PPP

Operators Annual Report


Input Data

Year HH C&I Clin RDF Total
2016 0.00 0.00 0.00 0.00 0.00
2017 0.00 0.00 0.00 0.00 0.00
2018 218061.00 89507.00 0.00 0.00 307569.00
2019 274318.00 20296.00 0.00 0.00 294614.00
2020 273182.00 26866.00 0.00 0.00 300048.00
2021 234216.00 69020.00 0.00 0.00 303236.00
2022 244633.00 52806.00 9.00 0.00 297448.00


Output Data

Year IBA IBA %ge of Tot IN APC APC %ge of Tot IN
2016 55427.79 0.00% 11007.96 0.00%
2017 54026.00 0.00% 12174.00 0.00%
2018 59159.00 19.23% 12112.00 3.94%
2019 46333.00 15.73% 10789.00 3.66%
2020 51374.00 17.12% 11359.00 3.79%
2021 58700.00 19.36% 11396.00 3.76%
2022 65038.00 21.87% 7667.00 2.58%

Summary

An EfW facility based upon conventional combustion technology and considered an ERF based on its R1 status. Greatmoor has permitted operational capacity of 345,000 tonnes per annum, operated by FCC Environment in a partnership with Buckinghamshire County Council . Delivery of waste is by road and the facility processes primarily residual Household Waste and some Commercial Waste[1].

History

The Greatmoor facility was built primarily to service a 30 year PFI contract signed in April 2013 with Buckinghamshire County Council, with anticipated total throughput of up to 345,000 tonnes per annum. It is located on FCC Environment's Calvert Landfill in the north of Buckinghamshire[2].

Plant

Built by Hitachi Zosen Inova under a Design & Build EPC-turnkey contract . Construction started in September 2013 and was completed in June 2016 at a reported[3] GBP £210m capital cost. The plant comprises 1 line of 37.5 tonnes/hour (maximum 39.4 tonnes/hour) with a design capacity capable of treating 300,000 tonnes per annum via standard combustion technology, air cooled, Hitachi Zosen Inova Grate, generating super-heated steam, and is configured to run on residual Household Waste and Commercial Waste with a CV of between 7.5 and 12.5MJ/kg delivering between 27.7 MWe and 29.4 MWe output with up to 6.6 MWth of district heating output.

Local Authority Users

References