Runcorn EfW: Difference between revisions

→‎History: explanation of GMWDA
m (→‎Plant: Typo)
(→‎History: explanation of GMWDA)
Line 7: Line 7:


==History==
==History==
The Runcorn facility was built in two phases with 425,000 tonnes per annum capacity in each phase. The initial capacity focused on the solution delivered as part of the [[PFI]] for [[Greater Manchester Combined Authority | GMWDA]] and was then subsequently extended to deliver a capacity of 1,100,000 tonnes per annum to reflect the lower [[Calorific Value]] of the fuel delivered than was anticipated in the design for 850,000 tonnes per annum. The facility is a [[CHP]] plant, located on [[Ineous Chlor]]'s site in Runcorn, generating 83MWe of electricity (design point vs 100MWe listed capacity) and 51MWth of heat for the adjacent chemical manufacturing site  
The Runcorn facility was built in two phases with 425,000 tonnes per annum capacity in each phase. The initial capacity focused on the solution delivered as part of the [[PFI]] for [[Greater Manchester Combined Authority | GMWDA]] (Greater Manchester Waste Disposal Authority, now Greater Manchester Combined Authority) and was then subsequently extended to deliver a capacity of 1,100,000 tonnes per annum to reflect the lower [[Calorific Value]] of the fuel delivered than was anticipated in the design for 850,000 tonnes per annum. The facility is a [[CHP]] plant, located on [[Ineous Chlor]]'s site in Runcorn, generating 83MWe of electricity (design point vs 100MWe listed capacity) and 51MWth of heat for the adjacent chemical manufacturing site
 
==Plant==
==Plant==
Built by [[Keppel Seghers]] under a Design & Build [[EPC]]-turnkey contract. Phase 1 commenced in 2009 and was handed over in January 2015, and phase 2 commenced in 2010 and handed over in April 2015 at a contract value of GBP £390 million <ref>[http://www.keppelseghers.com/en/content.aspx?sid=3028 Keppel Sehers Website]</ref>.
Built by [[Keppel Seghers]] under a Design & Build [[EPC]]-turnkey contract. Phase 1 commenced in 2009 and was handed over in January 2015, and phase 2 commenced in 2010 and handed over in April 2015 at a contract value of GBP £390 million <ref>[http://www.keppelseghers.com/en/content.aspx?sid=3028 Keppel Sehers Website]</ref>.
banneredit
1,703

edits