==Technology== | ==Technology== | ||
The plant technology will comprise a single line of a standard moving grate technology, processing around 44 tonnes per hour of waste and producing super-heated steam and 40MWe with a net export of 35MWe and 12MWth of heat<ref>Permit Application to SEPA</ref> | The plant technology will comprise a single line of a standard moving grate technology, processing around 44 tonnes per hour of waste and producing super-heated steam and 40MWe with a net export of 35MWe and 12MWth of heat<ref>Permit Application to SEPA</ref>. The [[grate]] and boiler was reported in July 2022 as being delivered by [[Hitachi Zosen Inova Steinmüller]]<ref>[https://www.letsrecycle.com/news/hzi-steinmuller-chosen-for-south-clyde-efw-plant/ Linked in Article accessed 22nd July 2022]</ref>. | ||
==Construction== | ==Construction== | ||
The plant will be constructed under an [[EPCM]] arrangement with [[AFRY]] in co-operation with [[AFRY Solutions UK Ltd]] and [[AFRY Finland Oy]]. | The plant will be constructed under an [[EPCM]] arrangement with [[AFRY]] in co-operation with [[AFRY Solutions UK Ltd]] and [[AFRY Finland Oy]]. | ||
==Waste Input== | ==Waste Input== |